We bid the set / not a guess
Send the drawings and the roof spec. We review the assembly, attachment, slope, and
tie-ins and return material, attachment pattern, warranty, and schedule in writing.
If the spec permits alternates we price them so you can see the trade-off.
02
Prequal package, ready
Licence, certificate of insurance, W-9, and our written safety program and drug-free
workplace policy. Tell us your bonding requirement and we will confirm capacity with our
agent rather than guessing at it.
03
We flag it at bid
If something in the drawings will cause a problem in the field — a detail that
cannot be flashed, a slope that will not drain, a product that will not get approval
— you hear it during bidding. Not as a change order in month four.
04
Daily logs to your PM
Crew count, work completed, photographs, and anything that will affect the look-ahead.
Your superintendent should not have to climb a ladder to find out where the roof stands.